IS 410 in San Antonio Open?

San Antonio Area Freeway System
PROJECT INFO: Loop 410 from Ingram to US 90

This page last updated August 20, 2022


IS 410 in San Antonio Open?
Location
Loop 410/SH 151 interchange including Loop 410 from Ingram Rd. to US 90
Status
Phase 1: Completed in 2018
Phase 2: Under construction (93% complete)

Timeline
Work on Phase 2 started in August 2019 and is expected to be complete in late 2022.
The eastbound SH 151 to southbound Loop 410 flyover opened on September 15, 2021.
The northbound Loop 410 to westbound SH 151 flyover opened on October 9th, 2021.
Future projects to complete the remainder of the SH 151/Loop 410 interchange are currently unfunded and therefore have no timeline.

Description
Phase 1 of this $81.8 million project constructed the first two flyovers at the interchange at Loop 410 and SH 151, widened Loop 410 to eight lanes from Ingram to SH 151, and made various ramp improvements on Loop 410 and on SH 151.

Phase 2 will build the eastbound SH 151 to southbound Loop 410 and northbound Loop 410 to westbound SH 151 flyovers. This project will also widen Loop 410 to ten lanes from Ingram to SH 151 and to eight lanes from SH 151 to US 90.

How this project will help
The additional flyovers at the Loop 410/SH 151 interchange will improve operations and reduce congestion in the interchange and adjacent access roads. The additional lanes on Loop 410 should accommodate expected future traffic volumes.

FAQ

  • Why is construction starting again less than a year after the first phase was completed and before the work south of SH 151 is done?
    This is because TxDOT's funding was increased significantly a few years ago, so backlogged projects are getting funded much sooner than expected. Phase 2 of this project is one of those backlogged projects that has been expedited due to the new funding; it was originally expected there would be five or more years between phases.
  • Why did work stop for so long on the flyovers in Phase 1?
    After work had started, an engineering error was discovered in the plans for the long steel beams which delayed their fabrication. In the meantime, in order to prevent the overall project from being delayed, the contractor worked on other areas of the project out-of-sequence, i.e. work that was scheduled to be done after the flyovers were completed was expedited. Therefore, while this issue did delay the opening of the flyovers, it did not cause any delay in the overall completion date of the project.

Schematic
Click on the image below to open the detailed schematic for this project (Phase 2) from TxDOT with my own annotations added to help clarify and explain the various elements. The schematic will open in a new window that you can scroll and zoom. 


DETAILED PROJECT SCHEMATIC

IS 410 in San Antonio Open?

Click above to see the detailed annotated schematic for this project


Other sites of interest

Drivers can expect several construction-related road closures along I-10, I-35, Loop 410, Loop 1604, US 281, US 90

Drivers can expect several construction-related road closures along I-10, I-35, Loop 410

This article is updated each week. For more information on transportation and traffic, including alerts, travel times and maps, view KSAT’s traffic page. To view more on the current weather conditions, click here. See low-water crossing closures here. Have a question? Get in touch here.

Last updated: September 5, 2022

According to TxDOT, there will be several closures taking place through the month of September. Make sure to plan ahead.

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North West San Antonio/Bexar County

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating westbound mainlane closure from IH-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding Weekends.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane full closure from Babcock Road to La Cantera Parkway for bridge construction – rail demo. Only one full mainlane closure to occur per direction, per night.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Westbound mainlane full closure from La Cantera Parkway to Babcock Road for bridge construction – rail demo. Excluding Weekends. Only one full mainlane closure to occur per direction, per night.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and Bandera Road (SH 16) in both directions, including turnarounds, for bridge construction – formwork removal.

  • Tuesday, September 6 until Friday, September 9. Weeknights 9 p.m. until 5 a.m. Full intersection closure at Loop 1604 and La Cantera Parkway/John Peace Boulevard in both directions, including turnarounds, for bridge construction – rail demo.

  • Tuesday, September 6 until Thursday, September 15. Weeknights 9 p.m. until 5 a.m. Westbound mainlaine exit ramp full closure to the westbound frontage road from the IH-10 interchange approaching La Cantera Parkway for portable concrete traffic barriers. Nightly lane closure. Excluding Weekends. Two consecutive ramps will not be closed at the same time at any point. No closures to occur from September 2 until September 5.

  • Tuesday, September 6 until Thursday, September 15. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane entrance ramp full closures from La Cantera Parkway for portable concrete traffic barriers. Nightly lane closure. Excluding Weekends. Two consecutive ramps will not be closed at the same time at any point. No closures to occur from September 2 until September 5.

  • Tuesday, September 6 until Thursday, September 15. Weeknights 9 p.m. until 5 a.m. Eastbound mainlane exit ramp full closure to Vance Jackson Road for portable concrete traffic barriers. Nightly lane closure. Excluding Weekends. Two consecutive ramps will not be closed at the same time at any point. No closures to occur from September 2 until September 5.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Alternating eastbound frontage road lane closure from Bandera Road (SH 16) to IH-10 for sidewalk construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Alternating westbound frontage road lane closure from IH-10 to Bandera Road (SH 16) for sidewalk construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Babcock Road for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and Chase Hill Boulevard/Brennan Avenue for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.

  • Tuesday, September 6 until Monday, September 12. Weekdays 9 a.m. until 3 p.m. Eastbound to westbound turnaround closure at Loop 1604 and La Cantera Parkway for bridge widening. Alternating. Only one turnaround to be closed at a time. Excluding Weekends.

Loop 1604 – North Central San Antonio/Bexar County

  • Sunday, September 4 until Friday, September 9. Nightly 9 p.m. until 5 a.m. Alternating eastbound mainlane closure from Tradesman Road to US 281 exit ramp for barrier setting and striping.

  • Sunday, September 4 until Friday, September 9. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlane closure from US 281 exit ramp to Tradesman Road for barrier setting and striping.

  • Sunday, September 4 until Friday, September 9. Nightly 9 p.m. until 5 a.m. Alternating eastbound frontage road closure from IH-10 to US 281 for barrier setting and striping.

  • Sunday, September 4 until Friday, September 9. Nightly 9 p.m. until 5 a.m. Alternating westbound frontage road closure from US 281 to IH-10 for barrier setting and striping.

  • Sunday, September 4 until Friday, September 9. Nightly 9 p.m. until 5 a.m. Westbound to eastbound turnaround full closure at Loop 1604 and NW Military Highway for drilling shafts.

  • Sunday, September 4 until Friday, September 9. Nightly 9 p.m. until 5 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and Huebner Road for wall excavation.

  • Monday, September 5 until Friday, September 9. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround full closure at Loop 1604 and Lockhill Selma Road for drilling shafts.

  • Monday, September 5 until Friday, September 9. Weekdays 9 a.m. until 3 p.m. Westbound to eastbound turnaround short term full closure at Loop 1604 and NW Military Highway for concrete placement for drilling shafts.

  • Monday, September 5 until Friday, September 9. Weekdays 9 a.m. until 3 p.m. Northbound Lockhill Selma Road right turn lane closure to eastbound Loop 1604 frontage road for traffic signal work.

  • Sunday, September 4 until Sunday, September 11. Weekdays/Weeknights 12 a.m. until 12 a.m. Eastbound to westbound turnaround full closure at Loop 1604 and NW Military Highway for bridge widening construction.

Loop 1604 – North East San Antonio/Bexar County

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound Loop 1604 from Nacogdoches Road to I-35 for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 from I-35 to Nacogdoches Road for barrier work.

  • Tuesday September 6 until Saturday September 10 10:00 PM to 05:00 AM. Alternating lane closures on eastbound frontage road of Loop 1604 from Nacogdoches Road to Union Pacific Railroad for excavation work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Lookout Road exit ramp closure on eastbound Loop 1604 between Nacogdoches Road and Union Pacific Railroad for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound frontage road bypass of Loop 1604 from Union Pacific Railroad to Lookout Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on Lookout Road from eastbound frontage road of Loop 1604 to westbound frontage road of Loop 1604 for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on Loop 1604 eastbound frontage road from Lookout Road to IKEA - RBFCU Parkway for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Entrance ramp closure of eastbound Loop 1604 from Lookout Road to IKEA - RBFCU Parkway for striping and barrier work. Traffic must use the next entrance ramp.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on frontage road of westbound Loop 1604 from Gateway Boulevard to Lookout Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Closure of westbound Loop 1604 exit ramp from Gateway Boulevard to Lookout Road for barrier work. Traffic must use Lookout Road exit.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Closure of westbound Loop 1604 exit ramp from Gateway Boulevard to Lookout Road for barrier work. Traffic must use the Nacogdoches Road to access Lookout Road.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on westbound Loop 1604 bypass from Lookout Road to Union Pacific Railroad for barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Westbound Loop 1604 exit ramp closure and left lane ramp closure from Union Pacific Railroad to Nacogdoches Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on westbound frontage road of Loop 1604 from Union Pacific Railroad to Nacogdoches Road for barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on frontage road of Loop 1604 westbound-to-eastbound turnaround from Lookout Road and Union Pacific Railroad for barrier work.

US 281 – North San Antonio/Bexar County

  • Friday, September 16. 8 p.m. to 5 a.m. Full closure of the intersection at Wilderness Oak for bridge work.

  • Tuesday, September 2. 8 p.m. to 5 a.m. Full closure of the intersection at Overlook Parkway for bridge work.

I-35 – Central San Antonio/Northeast San Antonio/New Braunfels/Comal County

  • Tuesday, September 6. 10:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and left lane closure on connector ramp from Forum Parkway to Loop 1604 for crash cushion attenuator repair.

  • Tuesday, September 6. 10:00 p.m. to 5:00 a.m. Full ramp closure and left lane closure on southbound I-35 frontage road from Retama Parkway to Utopia Boulevard for crash cushion attenuator repair.

  • Tuesday, September 6. 10:00 p.m. to 5:00 a.m. Right shoulder closure on westbound Loop 410 connector ramp for crash cushion attenuator repair.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35, left lane closure on southbound frontage road of I-35 and closure of southbound I-35 entrance ramp from Pat Booker Road to Ferrell Road for barrier work. Traffic must continue straight to Judson Road entrance ramp.

  • Tuesday, September 6 until Saturday, September 10. 9 p.m. to 5 a.m. Multiple lane (2) closures in both directions from Watson Bridge to FM 306 for drainage and pavement work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Right lane closure on southbound I-35 and exit ramp closure of southbound I-35 from Toepperwein Road to Judson Road for barrier work. Traffic must use O’Connor Road exit.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Left lane closure on southbound I-35 frontage road and exit ramp closure from Ferrell Road to Judson Road for barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on eastbound and westbound Toepperwein Road from southbound frontage road of I-35 to northbound frontage road of I-35. for barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Multiple lane (3) closures on southbound I-35 and connector ramp closure from Thousand Oaks Drive to Walzem Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closure on southbound I-35 connector ramp from eastbound I-410 to Walzem Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Alternating lane closures on southbound frontage road of I-35 from Thousand Oaks Drive to Walzem Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Multiple lane (3) closures on southbound I-35 from Forum Parkway to Ferrell Road for striping and barrier work.

  • Tuesday, September 6 until Saturday, September 10. 10:00 p.m. to 5:00 a.m. Mobile operation on southbound I-35 mainlane from Judson Road to O’Connor Road for raised pavement marker work.

  • Sunday, September 11 until Monday, September 12. 10 p.m. to 5 a.m. All north and southbound mainlanes from Watson Bridge and FM 306 will be closed for overhead bridge sign work.

I-10 – East San Antonio/Bexar County

  • Tuesday, September 6 until Friday, September 9. 8 p.m. to 6 a.m. Single eastbound mainlane closure from FM 2538 to FM 465 for barrier work.

  • Continuing through Tuesday, September 16. I-10 EB exit to Ackerman closed continuously for overpass work. Detour: Eastbound I-10 traffic can exit at Foster Road, turn around at intersection, and use westbound frontage road back to Ackerman. Click here for detour map.

  • Friday, September 9 9 p.m. to Monday, September 12 5 a.m. Full closure of the westbound mainlanes from Pfeil Rd. to Loop 1604.

I-410 – East San Antonio

  • Saturday, September 3 and Saturday, September 10 (Saturdays only). Daytime northbound and southbound I-410 alternating lane closures between Rigsby Avenue and FM 78 from 8 a.m. to 5 p.m. for pavement work.

  • Continuing through Sunday, September 11. DAYTIME northbound I-410 frontage road left lane closures between East Houston Street and I-10 from 8 a.m. to 5 p.m. for wall work.

  • Continuing through Sunday, September 11. DAYTIME southbound I-410 frontage road alternating lane closures between I-10 and East Houston Street from 8 a.m. to 5 p.m. for roadwork.

  • Tuesday, September 6 through Monday, September 19. NIGHTTIME northbound I-410 frontage road closure from East Houston Street on-ramp to eastbound I-10 from 9 p.m. to 5 a.m. (No closures Friday or Saturday Night.) Detour: Northbound I-410 traffic to Ackerman Road may take northbound I-410 to I-10 EB exit ramp, turn around at Foster Road, and take I-10 westbound frontage road to Ackerman.

  • Continuing through Monday, September 12. DAYTIME intersection closure at Cornerway Boulevard at I-10 westbound frontage road from 9 a.m. to 4 p.m. to install manholes. Cornerway detour: Use Dietrich Road as detour to access Cornerway Blvd.

  • Continuing through Wednesday, September 7. NIGHTTIME northbound I-410 exit to eastbound I-10 closure from 8 p.m. to 5 a.m. for barrier repair. Click here for detour map.

I-410 – West San Antonio

  • Tuesday, September 13 until Tuesday, September 27. 7 p.m. to 5 a.m. Alternating mainlane closures, in both directions, from Ingram Rd. to US 90 for pavement operations.

US 87 – Rigsby Road

  • Current until Monday, September 19. 9 a.m. to 4 p.m. Alternating lane closures, in both directions, from Roland Ave. to Loop 410 for striping operations.

US 181 – Bexar County

  • Current until Monday, September 19. 9 p.m. to 5 a.m. Alternating lane closures, in both directions, from Wilson County Line to I-37 for bridge work and striping operations.

I-10 – Kendall County

  • Sunday, August 28 until Friday, October 28. 9 p.m. to 5 a.m. Single mainlane closures, in both directions, from US 87 to FM 473 for pavement operations.

  • Thursday, September 1. 9 a.m. to 3 p.m. Single westbound mainlane closure from Scenic Loop Rd. to Ramp 542 for utility work.

I-35 – Frio County

  • Thursday, September 8 until Friday, September 9. 7:30 a.m. to 5 p.m. Moving operations from US 57 to the Frio/Medina County Line for pavement data collection.

See TxDOT’s map of current road closures below.